Waaree Energies commissions 27.5 MWp Solar Project for Roha Dyechem at Bhadla Solar Park
Being commissioned in a record time of 116 days
October 19, 2015. By Moulin
Waaree Energies Limited has announced the commissioning of 27.5 MW DC solar power plant for RohaDyechem Pvt Ltd at Bhadla Solar Park in Rajasthan. Sprawling across 125 acres, the project is first-of-its-kind and holds its differentiation of being commissioned in a record time of 116 days.
This project was allocated to RohaDychemPvt Ltd under the Rajasthan Solar Policy 2011 (Phase 1) with a 25 year PPA(Power Purchase Agreement) with Rajasthan Renewable Energy Corporation Limited (RRECL). Waaree Energies was engaged by RohaDychem as an end-to-end EPC( Engineering Procurement Construction) solution Provider. The Project utilizes 305 Wp and 310 Wp polycrystalline Solar Panels and 750 kW TMEIC Central Inverter. This is the second largest project commissioned by Waaree Energies Ltd after its 50 MW project for Waaneep Solar during 2015.
Commenting on the completion of this prestigious project, Mr. Hitesh Doshi, Chairman and Managing Director, Waree energies, said, “We are glad to announce the commissioning of the project as it reiterates our commitment towards high quality both in terms of seamless execution and time-bounded delivery mechanisms. Our execution team battled the scorching heat during the peak summer time in Rajasthan and succeeded in achieving our target of commissioning 27.5 MW project in pre-decided time-frame. Our team was focused on the goals and had a highly result oriented approach.”
Speaking on the occasion, Shri Ramakantji Tibrewal, CMD, Roha Dychem Private Limited, said, “We as a nation aspire to be one of the top destinations in the manufacturing of solar energy that leads to sustainable development. We believe this is a step in that direction, thanks to consistent cooperation and support from Waree Energies. This project has strengthened our trust on the company and has paved the way towards long-term relationship to achieve the desired outcome in the future.”