Powergrid has successfully completed and charged 220 kV S/c Leh - Khalsti Line section of 220 KV S/c Alusteng (Srinagar) - Leh Transmission line, along with 220/66 kV GIS sub-stations at Leh and Khalsti on 31st Oct'17. This is the first time in the country that any 220kV voltage level substation is built at such a high altitude of over 11500 ft. 

This is a prestigious project of Govt. of India for extending Grid connectivity to difficult Geographical areas of Leh- Ladhakh Region in Jammu & Kashmir. Foundation of this strategically important project was laid by the Prime Minister in Aug.’14 (12.08.2014). Implementation of Srinagar-Leh Transmission System has been entrusted to Power Grid Corporation of India Limited (POWERGRID). 

Commissioning of these elements will facilitate delivery of power from the Nimmo Bazgo (3x15MW) Hydro-electric power stations in Leh/Ladhakh Region, with reliability. 

Balance sections of this project, namely Khalsti-Kargil-Drass-Alusteng(Srinagar) section is under progress, which upon completion, will facilitate Transfer of power to Ladakh region, directly from Northern Grid, in all seasons, with reliability. 

Smart Grid / T&D | News published on 03/11/2017 by Rashmi Nargundkar

 
 
Next events

 

Last interview
 
 
 Energetica India is a publication from Editorial Omnimedia. No reproduction in whole or part of content posted on this website.