Vestas secures 86 MW EPC deal with Nexif Energy for Lincoln Gap Wind Farm in Australia

The EPC agreement will include the engineering, procurement, and construction of 24 of Vestas' V136-3.45 MW turbines delivered in 3.6 MW Power Optimised Mode. This will add to the customer's existing fleet of 126 MW of Senvion turbines which are being serviced by Vestas

August 18, 2020. By News Bureau

Tags:

Vestas has announced that it has signed 86 MW contract with Nexif Energy for the second stage of the Lincoln Gap Wind Farm in South Australia. The EPC agreement will include the engineering, procurement and construction of 24 of Vestas' V136-3.45 MW turbines delivered in 3.6 MW Power Optimised Mode. This will add to the customer's existing fleet of 126 MW of Senvion turbines which are being serviced by Vestas.

By replacing Senvion as the EPC contractor, the project is on course to successfully meet Nexif Energy's long-term sustainable goals for South Australia. Upon completion, Vestas will commence a 20-year Active Output Management 5000 (AOM 5000) service agreement for the new turbines. This is designed to maximise energy production for the lifetime of the project. With an energy-based availability guarantee which covers both the turbines and balance of plant assets, Vestas will provide Nexif with long-term business case certainty.

"Vestas shares Nexif Energy's commitment for a sustainable future. Offering our world-leading energy solutions, we are pleased to continue our partnership and expand both the Lincoln Gap Wind Farm and Australia's renewable energy footprint," says Clive Turton, President of Vestas Asia Pacific.

The Lincoln Gap extension demonstrates Vestas' expertise across wind turbine brands through our ability to integrate the existing Senvion fleet with our turbines, and successfully export to the grid.

"Our ability to connect Senvion and Vestas turbines of the same wind farm to the grid, is an Australian first. We've combined our grid expertise, wind generation solutions and comprehensive knowledge of Senvion technology to make the expansion of Lincoln Gap a reality", says Peter Cowling, Head of Vestas Australia and New Zealand.

"Nexif Energy is pleased to appoint Vestas as its EPC contractor and long-term maintenance service provider for Stage 2 of our Lincoln Gap Wind Farm", said Charles Rattray, Managing Director at Nexif Energy. "This completes the transition from Senvion, following its insolvency, with construction of Stage 2 and the operating, and maintenance and performance of the entire windfarm in the hands of a leading industry services provider – Vestas. Nexif Energy is now well positioned to focus on the implementation on its further expansion plans for the wind farm and at other sites within South Australia and Australia more broadly".

Delivery of the turbines will commence in the first quarter of 2021, with commissioning to be scheduled in the third quarter of 2021. In addition, there will be over 80 employees on site during the main construction period of the project.

Please share! Email Buffer Digg Facebook Google LinkedIn Pinterest Reddit Twitter
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
 
 
 
Next events

 

Last interview
 
 
 Energetica India is a publication from Editorial Omnimedia. No reproduction in whole or part of content posted on this website.