HomeRenewable energy ›Shift to Auctions Leaves Irish Wind Vulnerable to Mid-Term Slump

Shift to Auctions Leaves Irish Wind Vulnerable to Mid-Term Slump

It plans to hold four auctions between 2020 and 2027 to deliver the targets, the Irish government said. It will be open to onshore and offshore wind, as well as solar, in a bid to diversify the country’s energy mix

December 03, 2019. By News Bureau

The Renewable Electricity Support Scheme (RESS) auction will begin by increasing renewables capacity in Ireland by 30%. It aims to get renewables to 70% of the country’s demand by 2030.

It plans to hold four auctions between 2020 and 2027 to deliver the targets, the Irish government said. It will be open to onshore and offshore wind, as well as solar, in a bid to diversify the country’s energy mix.

However, according to the Irish Wind Energy Association (IWEA), the current timeline will see a vacuum between the completion of projects under the current, outgoing support scheme and the successful projects in the new system.

"Ireland is already far behind on cutting our CO2 emissions and we are looking at a gap of 18 months between the completion of the last wind farms under the old REFIT support scheme and the connection of new projects under the RESS," said IWEA CEO David Connolly.

"Anything the government can do to get RESS up and running more quickly will save time, money and CO2 emissions," Connolly added.

Lessons could be taken from the stuttering German market, where a mismanaged shift to auctions has resulted in a sudden drop in installations and far-reaching consequences.

Tags:
Please share! Email Buffer Digg Facebook Google LinkedIn Pinterest Reddit Twitter
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
 
 
Next events
 
 
Last interviews
 
Follow us