ReNew, Purvah Green Power Win NPCL’s 300 MW RTC RE Power Auction
ReNew and Purvah Green Power have won a combined 300 MW RTC renewable energy tender floated by Noida Power Company, securing tariffs of INR 4.43/kWh and INR 4.44/kWh, respectively.
November 26, 2026. By Mrinmoy Dey
ReNew and Purvah Green Power have emerged as winners in Noida Power Company’s (NPCL) auction to procure 300 MW of round-the-clock (RTC) renewable power integrated with energy storage.
ReNew has won 85 MW at the L1 price of INR 4.43/kWh. Purvah Green Power has secured the balance 215 MW at a tariff of INR 4.44/kWh.
The tender for this was floated in September 2026.
Under the tender conditions, the developer must ensure at least 90 percent availability in each 15-minute time block and meet the specified power supply requirements during six designated peak hours. The project must also maintain a minimum annual capacity utilisation factor (CUF) of 75 percent, with a permitted variation of ±10 percent, throughout the contract period.
The project will have a fixed tariff for 25 years, with liquidated damages equivalent to 1.5 times the applicable tariff for any energy shortfall. The developer must ensure that the energy storage system (ESS) is charged using renewable energy within 24 months of the project timeline to support round-the-clock clean power supply to NPCL consumers in Greater Noida.
NPCL will have the flexibility to designate six hours each day as peak hours, requiring the project to ensure continuous power supply for at least one hour daily during the periods of 00:00–10:00 hrs. and 18:00–24:00 hrs. The designated peak hours will be communicated by NPCL a day in advance and will apply for the following day.
ReNew has won 85 MW at the L1 price of INR 4.43/kWh. Purvah Green Power has secured the balance 215 MW at a tariff of INR 4.44/kWh.
The tender for this was floated in September 2026.
Under the tender conditions, the developer must ensure at least 90 percent availability in each 15-minute time block and meet the specified power supply requirements during six designated peak hours. The project must also maintain a minimum annual capacity utilisation factor (CUF) of 75 percent, with a permitted variation of ±10 percent, throughout the contract period.
The project will have a fixed tariff for 25 years, with liquidated damages equivalent to 1.5 times the applicable tariff for any energy shortfall. The developer must ensure that the energy storage system (ESS) is charged using renewable energy within 24 months of the project timeline to support round-the-clock clean power supply to NPCL consumers in Greater Noida.
NPCL will have the flexibility to designate six hours each day as peak hours, requiring the project to ensure continuous power supply for at least one hour daily during the periods of 00:00–10:00 hrs. and 18:00–24:00 hrs. The designated peak hours will be communicated by NPCL a day in advance and will apply for the following day.