Rajasthan Sets Commissioning Deadlines for 6,000 MWh BESS Projects
Rajasthan sets November 2027 deadline for commissioning 6,000 MWh of battery energy storage projects.
November 27, 2026. By EI News Network
The Rajasthan government has set commissioning timelines for 6,000 MWh of battery energy storage system (BESS) projects across the state, with the entire capacity scheduled to become operational by November 2027.
The initiative aims to strengthen the state's energy storage infrastructure, improve grid reliability and facilitate greater integration of renewable energy.
Rajasthan Energy Minister Heeralal Nagar reviewed the progress of the projects during a meeting at Vidyut Bhawan in Jaipur, attended by senior officials of the Energy Department, Rajasthan Rajya Vidyut Utpadan Nigam (RVUN) and project developers selected through NTPC Vidyut Vyapar Nigam (NVVN).
During the meeting, the minister reviewed project implementation schedules, construction activities, land availability, grid connectivity and regulatory clearances. He directed officials to closely monitor project execution and warned developers of strict action in the event of delays.
Nagar instructed JSW to complete its 250 MWh battery storage projects at Giral and Suratgarh by December 2026, while deadlines for the remaining projects range from December 29, 2026, to November 7, 2027. He also assured developers of necessary government support and coordination to resolve challenges affecting project implementation.
The projects have been awarded under the central government's Viability Gap Funding (VGF) and Power System Development Fund (PSDF) schemes.
Of the total capacity, 1,000 MWh each has been allocated under the state and central components, featuring a two-hour storage duration and two charging-discharging cycles. Another 4,000 MWh has been awarded under the PSDF scheme, comprising 2,000 MWh with a two-hour, two-cycle configuration and 2,000 MWh with a four-hour, single-cycle configuration.
The projects were awarded at tariffs ranging from INR 1.77 lakh to INR 2.85 lakh per MW per month, which were reported to be the lowest in the country at the time of procurement.
Once operational, the battery storage systems will enable Rajasthan to store surplus renewable energy generated during periods of high solar and wind power production and discharge it during peak demand hours. The projects are expected to enhance grid flexibility, address renewable energy intermittency and facilitate electricity supply at competitive rates during peak demand periods.
The development comes as Rajasthan continues to expand its renewable energy capacity while strengthening its power storage infrastructure to ensure a reliable and cost-effective electricity supply.