Promotion of Grid Interactive biomass power & Bagasse Cogeneration in Sugar mills
Continuation of Scheme during the 12th Plan Period
July 07, 2014. By Moulin
MNRE sanctions continuation of the Plan scheme viz. "Promotion of Grid Interactive Biomass Power and Bagasse Cogeneration in Sugar Mills" during the 12th Plan period at a total cost of Rs.310 crores .The Scheme would be applicable from the date of 1st April, 2014 and would continue upto the end of 12th Five-Year Plan i.e. 31 March 2017
The scheme provides for grant of Central Financial Assistance (CFA) for setting up biomass combustion based power projects and bagasse cogeneration projects in private/cooperative/public sector sugar mills. The Ministry of New and Renewable Energy will continue to provide financial support for R&D activities, organization of Seminars/Symposiums/Workshops/Training programmes, strengthening of technical institutions, testing facilities, engaging consultants, undertaking studies etc. on case to case basis.
Grid connected Biomass Power and Bagasse Cogeneration Projects with the following capacity/parameters will only be eligible under the scheme:
|
Biomass Power (combustion) |
|
• Minimum 60 bar steam pressure • Maximum of upto 15% use of fossil fuel of total energy consumption in K. cals or as per DPR, whichever is less. • For only new boilers and turbines (capacity limited to in accordance with the estimated potential in a state) |
|
Bagasse Co-generation by Private/cooperative / Public Sector Sugar Mill |
|
• Minimum 40 bar steam pressure • Maximum of upto 15% use of fossil fuel of total energy consumption in K. cals. or as per DPR, whichever is less. |
|
Bagasse Cogeneration through BOOT/BOLT model by IPP's /State Govt. undertaking / State Govt. Joint Venture Company |
|
• Minimum 60 bar steam pressure • Maximum of upto 15% use of fossil fuel of total energy consumption in K. cals. or as per DPR, whichever is less, during crushing season. • Minimum export of power - 5 MW. |
|
Bagasse Cogeneration in existing cooperative sugar mill employing boiler modification |
|
• Minimum 40 bar steam pressure. • PPA as per SERC. • Maximum of upto 15% use of fossil fuel of total energy consumption in K. cals. or as per DPR, whichever is less, during crushing season. • Minimum export of power - 3 MW. |
Central Financial Assistance will be applicable for the projects started on 1st April, 2013 or later. For the projects started on or before 31st March, 2013, the old rate of CFA applicable during the 11th Five Year Plan and extended to 31st March, 2013 will be applicable.
For more information, please refer to the the attachment:
please contact: contact@energetica-india.net.