NTPC Green Energy Fully Commissions 1,200 MW Khavda-II Solar PV Project in Gujarat
NTPC Green Energy has fully operationalised its 1,200 MW Khavda-II Solar PV Project in Gujarat with the commissioning of the final 105 MW phase, taking the NGEL Group’s total installed capacity to 10,621.40 MW.
May 29, 2026. By Mrinmoy Dey
NTPC Green Energy (NGEL) has announced that the company, through its wholly-owned subsidiary NTPC Renewable Energy, has operationalised the eighth and the last part capacity of 105 MW at its 1,200 MW Khavda-II Solar PV Project located in Gujarat.
With this addition, the total installed capacity of the NGEL Group has increased to 10,621.40 MW, stated the company in a regulatory filing.
Last month, the company operationalised the seventh part capacity of 90 MW at the Khavda-II solar project.
In March 2026, the company operationalised the third, fourth, fifth and sixth part capacity totalling 630 MW. The second part capacity of 165 MW was operationalised in February 2026, while the first part capacity of 210 MW was operationalised in January 2026.
In March 2026, the company also operationalised the third and last part capacity of 75 MW at its 500 MW Bhadla solar PV project located in Phalodi, Rajasthan and the twelfth and the last part capacity of 78.02 MW at its 1,255 MW Khavda-I solar PV project located in Gujarat.
By 2032, NTPC Group plans to have 60 GW capacity through RE sources, constituting nearly 45 percent of its overall power generation capacity.
With this addition, the total installed capacity of the NGEL Group has increased to 10,621.40 MW, stated the company in a regulatory filing.
Last month, the company operationalised the seventh part capacity of 90 MW at the Khavda-II solar project.
In March 2026, the company operationalised the third, fourth, fifth and sixth part capacity totalling 630 MW. The second part capacity of 165 MW was operationalised in February 2026, while the first part capacity of 210 MW was operationalised in January 2026.
In March 2026, the company also operationalised the third and last part capacity of 75 MW at its 500 MW Bhadla solar PV project located in Phalodi, Rajasthan and the twelfth and the last part capacity of 78.02 MW at its 1,255 MW Khavda-I solar PV project located in Gujarat.
By 2032, NTPC Group plans to have 60 GW capacity through RE sources, constituting nearly 45 percent of its overall power generation capacity.