HomeEnergy Storage ›NTPC Green Energy Floats EPC Tender to Develop 3,300 MWh BESS at Khavda Solar Park in Gujarat

NTPC Green Energy Floats EPC Tender to Develop 3,300 MWh BESS at Khavda Solar Park in Gujarat

NTPC Green Energy has issued an EPC tender for setting up 1,100 MW/3,300 MWh battery energy storage systems at NTPC Renewable Energy’s Khavda Solar Plant in Rajasthan. Bid submission ends on June 25, 2026.

June 01, 2026. By Mrinmoy Dey

NTPC Green Energy has floated an EPC tender for the development of 1,100 MW/3,300 MWh Battery Energy Storage Systems (BESS) capacity at NTPC Renewable Energy’s Khavda Solar Plant in Gujarat.
 
The project is divided into four blocks. While three blocks will have a capacity of 300 MW/900 MWh each, the fourth block will have a capacity of 200 MW/600 MWh. The BESS must be connected at Pooling Sub Station-1 (PSS-1) of NTPC REL’s Khavda Solar Park in Gujarat. Each BESS block must be connected at the 33 kV level of a designated 300 MW solar plant.
 
The last date for submission of bids is June 25, 2026 till 3:00 PM. The techno-commercial bids will be opened on the same day at 3:30 PM.
 
The scope of work includes design, engineering, supply, packing and forwarding, transportation, unloading, storage, installation and commissioning of grid-connected BESS on a turnkey basis.
 
Design life of the BESS system, including that of the battery, shall be of 25 years (with degraded capacity as per the bidder’s proposal, considering daily single cycle operation) from the date of commissioning. Batteries offered must be rated for a minimum of 10,000 cycles of operation.
 
The bidders must also provide comprehensive operation and maintenance (O&M) for a period of 15 years.
 
Bidder will guarantee a minimum of 92 percent of dispatchable capacity at POI across all 15 years, starting with 100 percent of rated dispatchable capacity at CoD and 95 percent for the first year. Dispatchable capacity at the time of handover must be a minimum of 92 percent.
 
Minimum monthly Round Trip Efficiency (RTE) must be 80 percent including auxiliary consumption. Annual availability must be maintained at 98 percent.
  Download the attached file
Please share! Email Buffer Digg Facebook Google LinkedIn Pinterest Reddit Twitter
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
 
 
Next events
 
 
Last interviews
 
Follow us