NISE Offers INR 2 Crore Aid for DISCOM DERMS Pilots
NISE invites DISCOMs to deploy DERMS pilots with up to INR 2 crore in financial assistance.
November 25, 2026. By EI News Network
The National Institute of Solar Energy (NISE), on behalf of the Ministry of New and Renewable Energy (MNRE), has invited proposals from electricity distribution companies (DISCOMs) for the deployment of Distributed Energy Resource Management Systems (DERMS) under the Innovative Projects Component of the PM Surya Ghar: Muft Bijli Yojana. The last date for submission of proposals is December 20, 2026.
MNRE will provide financial assistance of up to 60 percent of the approved project cost, subject to a maximum of INR 2 crore per DISCOM. The top 15 proposals will be selected for financial support, subject to merit, budget availability and necessary approvals.
The initiative comes amid the rapid expansion of rooftop solar installations across India, with over 13,000 installations being recorded daily, according to the Call for Proposal (CfP). The increasing penetration of distributed energy resources, including rooftop solar systems, solar pumps, small photovoltaic grids, battery energy storage systems, electric vehicle (EV) charging infrastructure and demand response resources, has created a need for advanced digital distribution network management solutions.
The initiative seeks to promote real-time monitoring of rooftop solar generation, GIS-based mapping of distributed energy resources, renewable energy forecasting, voltage regulation, congestion management and dynamic hosting capacity assessment.
Other identified solution areas include consumer demand response platforms, smart load management, virtual power plants (VPPs), battery dispatch optimisation, community energy storage, managed EV charging, vehicle-to-grid (V2G) applications, artificial intelligence-based forecasting, digital twins, advanced analytics and blockchain-enabled energy transactions, subject to applicable regulations.
State-owned, private and joint venture DISCOMs, along with Power Departments operating electricity distribution networks in India, are eligible to participate. Only one proposal will be accepted from each DISCOM or Power Department, with each pilot project required to cover a minimum of one distribution division.
DISCOMs may engage system integrators, equipment suppliers, implementing agencies and technology or software providers through their respective procurement procedures. However, MNRE funding will not cover advisory, consultancy, detailed project report preparation or project management consultancy services.
The financial assistance will cover equipment and field hardware, software development, system integration, analytics, consumer interface development, demonstration activities and permissible organisational overheads. The balance of the approved project cost will be borne by the respective DISCOM.
The approved grant, excluding organisational overheads, will be released in two instalments, with 50 percent disbursed along with the sanction letter and the remaining amount released upon achieving specified project milestones. Organisational overheads will be restricted to 8 percent of the project cost excluding overheads, subject to a maximum of INR 15 lakh.
Proposals will be evaluated based on innovation and technical feasibility (30 percent), expected impact on grid operations (20 percent), scalability and replicability (20 percent), consumer benefits (15 percent) and cost-effectiveness (15 percent).
Selected DISCOMs will be required to complete their projects within six months from the issuance of the sanction letter. Deliverables include an operational DERMS platform, distribution-level visibility dashboards, rooftop solar database integration, forecasting and analytics engines, network hosting capacity assessments, performance assessment reports and roadmaps for utility-wide deployment.
please contact: contact@energetica-india.net.