Net Meter Shortage Stalls Rooftop Solar Installations in Telangana
A shortage of three-phase net meters in Telangana has stalled rooftop solar connections, leaving completed installations unable to supply power to the grid.
November 17, 2026. By EI News Network
Rooftop solar installations in Telangana are facing delays due to a shortage of net meters, particularly three-phase meters, preventing consumers from connecting completed solar power systems to the electricity grid.
Solar vendors have been making repeated visits to distribution company offices in search of meters, with several installations remaining idle for days. Without net meters, electricity generated by rooftop solar plants cannot be connected to the grid, leaving the installed capacity underutilised and causing financial losses to consumers and solar developers.
The shortage has resurfaced after limited stocks of three-phase net meters were exhausted. Meters received in August were distributed to stores in Hyderabad and other districts. However, the available stock was depleted within a month, with shortages emerging again from October. Around 2,000 pending meter requirements were cleared following subsequent supplies, but the availability of three-phase meters has again become a concern.
Officials of the Telangana Southern Power Distribution Company Ltd. (TGSPDCL) said 8,900 single-phase net meters were currently available. Another 4,000 meters are expected to arrive after Diwali.
Explaining the supply constraints, TGSPDCL said it had floated tenders and placed orders for net meters, but manufacturers were unable to meet delivery schedules due to a global shortage of electronic printed circuit board components. The utility had earlier placed orders for 15,000 net meters, of which 7,000 were received in August.
The shortage is affecting rooftop solar installations across the residential, commercial and industrial segments. Although solar plants have been installed and are ready to generate electricity, the absence of three-phase net meters is delaying their commissioning and grid connectivity.
According to Burra Ashok Kumar Goud, President of the Telangana Solar Energy Association, consumers continue to show interest in rooftop solar installations as they seek to reduce electricity bills. However, delays in meter availability are preventing completed projects from becoming operational, resulting in losses for both consumers and solar developers.