Home › Renewable energy ›Details of Projects sanctioned under Off Grid Solar applications of JNNSM during 2013-14
Details of Projects sanctioned under Off Grid Solar applications of JNNSM during 2013-14
363.08 crore CFA sanctioned to 70 companies
June 05, 2014. By Moulin
Ministry of New and Renewable Energy today released the details of projects sanctioned under Off Grid Solar applications of JNNSM during 2013-14. A total of 363.08 crore CFA was sanctioned to 70 companies and CFA of 15.72 crore was released.
| S.NO | STATE | Implementing Agency | Sanctioned Systems | Location | Date of sanction/ Date of Completion | Sanctioned | Released | Capacity | Status |
| MNRE CFA (Rs. In Crore) | CFA (Rs. In crore) | (kWp) | |||||||
| 1 | Andhra Pradesh | NREDCAP | Power packs | Throughout state | 05.03.2014 | 57.28 | - | 10000 | |
| 05.03.2015 | |||||||||
| 2 | Arunachal Pradesh | APEDA | Street Lights | NIT Jote | 31.12.2013 | 1.1 | - | 44 | |
| 31.12.2014 | |||||||||
| 3 | Chhattisgarh | CREDA | Power packs | Throughout state | 05.03.2014 | 3.18 | - | 500 | |
| 05.03.2015 | |||||||||
| 4 | CREDA | Power packs | Throughout state | 05.03.2014 | 6.36 | - | 1000 | ||
| 05.03.2015 | |||||||||
| 5 | Haryana | HAREDA | Power packs | Throughout state | 05.03.2014 | 0.6 | - | 105 | |
| 05.03.2015 | |||||||||
| 6 | Himachal Pradesh | HIMURJA | Lanterns (10000no.) | Kinnaur district | 11.09.2013 | 2.49 | 1.25 | 100 | Completed |
| 11.09.2014 | |||||||||
| 7 | HIMURJA | Power plants | For drinking water in Kangra | 31.12.2013 | 7.77 | - | 450 | ||
| 31.12.2014 | |||||||||
| 8 | Jammu &Kashmir | LREDA | Solar Pumps | Leh district | 31.12.2013 | 0.06 | - | 3 | |
| 31.12.2014 | |||||||||
| 9 | Manipur | MANIREDA | Power plants | Courts | 31.12.2013 | 2.67 | - | 155 | |
| 31.12.2014 | |||||||||
| 10 | Meghalaya | MNREDA | Power packs | CSCs | 31.12.2013 | 4.33 | - | 225 | |
| 31.12.2014 | |||||||||
| 11 | Nagaland | DNRE | Power plants/packs | CSCs | 31.12.2013 | 4.75 | - | 261 | |
| 31.12.2014 | |||||||||
| 12 | DNRE | Power packs | Throughout state | 05.03.2014 | 0.73 | - | 104 | ||
| 05.03.2015 | |||||||||
| 13 | Punjab | PEDA | Street | Throughout the state | 31.12.2013 | 1.63 | 366 | ||
| Lights/Power packs | 31.08.2014 | ||||||||
| 14 | Rajasthan | RRECL | Power Packs (2000no.) | Throughout the state | 05.03.3014 05.03.2015 | 12.72 | - | 2000 | |
| 15 | RRECL | Pumps (10000no.) | Throughout the state | 28.03.2013 28.03.2015 | 143.61 | 29920 | |||
| 16 | Tamilnadu | TEDA | Power Packs (2000no.) | Throughout the state | 05.03.3014 05.03.2015 | 12.12 | 2000 | ||
| 17 | Uttarakhand | UREDA | Lanterns (20000no.) | Flood affected districts | 29.08.2013 | 4.32 | 4 | 200 | Completed |
| 28.02.2014 | |||||||||
| 17 | Uttar Pradesh | UPNEDA | Street Lights (12453no.) | Lohia grams | 31.12.2013 | 7.54 | - | 922 | |
| 31.12.2014 | |||||||||
| 18 | Others | CEL | Power Plants (2no.) | West Bengal, Karnataka | 31.12.2013 | 0.81 | - | 210 | |
| 31.08.2014 | |||||||||
| 19 | CEL | Power plants 910no.) | Greater Noida | 31.12.2013 | 3 | 1000 | |||
| 31.08.2014 | |||||||||
| 20 | Chaitanya | Power Plants (24no.) | Branches of the bank | 31.12.2013 | 0.34 | 69 | |||
| Godavari | 31.08.2014 | ||||||||
| Bank | |||||||||
| 21 | IIT Mumbai | One million study lights | Madhya Pradesh, Maharashtra | 15.03.2014 | 14.81 | 10.36 | 1000 | ||
| 15.03.2015 | |||||||||
| 22 | PEC | Power plants (10no.) | Assam Rifles | 31.12.2013 | 5.1 | 1000 | 400kWp completed so far | ||
| 31.08.2014 | |||||||||
| 23 | REIL | Power plants (8no.) | Assam Rifles | 30.12.2013 | 4.08 | - | 800 | ||
| 30.08.2014 | |||||||||
| 24 | REIL | Power plants (16no.) | Rajasthan, Kerala | 31.12.2013 | 3.68 | - | 760 | ||
| 31.08.2014 | |||||||||
| 25 | SECI | Street Lights (500no.) | Jharkhand | 31.12.2013 | 0.15 | - | 37 | ||
| 31.08.2014 | |||||||||
| 26 | SECI | Power Plants (2no.) | Jammu & Kashmir ,Uttar Pradesh | 31.12.2013 | 0.88 | - | 76 | ||
| 31.08.2014 | |||||||||
| 27 | Channel Partners | Acva Solar Vadodra | Power Plants (27no.0 | Gujarat | 31.12.2013 | 0.93 | - | 299 | |
| 31.08.2014 | |||||||||
| 28 | ADS Projects New Delhi | Power Plants (5no.) | Uttar Pradesh | 30.12.2013 | 0.11 | 0.11 | 230 | Completed | |
| 31.08.2014 | |||||||||
| 29 | Aditi Solar Hyderabad | Power Packs | Govt Offices in West Godavari | 31.12.2013 | 1.82 | - | 375 | ||
| 31.08.2014 | |||||||||
| 30 | Aditya Green Latur | Power plants (33no.) | Maharashtra | 31.12.2013 | 2.4 | - | 737 | ||
| 31.08.2014 | |||||||||
| 31 | Agni Power Kolkata | Power | West Bengal Assam | 31.12.2013 | 1.87 | - | 240 | ||
| Plants/minigri | 31.08.2014 | ||||||||
| ds | |||||||||
| 32 | Bosch Ltd Bangalore | Power Plants (121no.) | Punjab Tamilnadu, Gujarat | 31.12.2013 | 1.36 | - | 398 | ||
| 31.08.2014 | |||||||||
| 33 | Bright solar Ahmadabad | Pumps (174no.) | Gujarat | 31.12.2013 | 3.66 | - | 746 | ||
| 31.08.2014 | |||||||||
| 34 | C& S | Power Plants (5no.) | Hyderabad Chennai | 31.12.2013 | 1.35 | 500 | |||
| Electric New Delhi | 31.08.2014 | ||||||||
| 35 | Chemtrols Mumbai | Power Plants (2no.) | Maharashtra Punjab | 31.12.2013 | 0.34 | - | 119 | Completed | |
| 31.08.2014 | |||||||||
| 36 | Consul Consolidate d Chennai | Power Plants (4no.) | Tamilnadu | 31.12.2013 | 0.48 | 148 | |||
| 31.08.2014 | |||||||||
| 37 | Deepa Solar Bangalore | Power | Karnataka | 31.12.2013 | 0.63 | - | 114 | ||
| Plants(28no.) | 31.08.2014 | ||||||||
| 38 | El-Sol | Power Plants (3no.) | Gujarat | 31.12.2013 | 0.9 | 300 | 100kWp installed so far | ||
| Energy | 31.08.2014 | ||||||||
| Ahmadabad | |||||||||
| 39 | Emeral Energy Ahmadabad | Power Plant | Gujarat | 31.12.2013 | 0.51 | 100 | Completed | ||
| 31.08.2014 | |||||||||
| 40 | Eversun | Power Plant | West Bengal | 31.12.2013 | 0.25 | 100 | |||
| Energy | 31.08.2014 | ||||||||
| Bangalore | |||||||||
| 41 | Exicom Tele Gurgaon | Power Plants (7no.) | Bihar | 31.12.2013 | 0.55 | - | 105 | ||
| 31.08.2014 | |||||||||
| 42 | Godrej Mumbai | Power Plants(3no.) | Karnataka, Kerala Haryana | 31.12.2013 | 0.44 | - | 134 | ||
| 31.08.2014 | |||||||||
| 43 | International | Power Plants(7no.) | Gujarat, Tamilnadu, Maharashtra | 31.12.2013 | 1.11 | 342 | 216kWp installed so far | ||
| Marketing, | 31.08.2014 | ||||||||
| Mumbai | |||||||||
| 44 | Jain Irrigation Jalgaon | Power | Maharashtra, Gujarat, Punjab | 31.12.2013 | 1.49 | - | 370 | ||
| plants/Pumps | 31.08.2014 | ||||||||
| 45 | Jaiswal batteries Lucknow | Power Plants (2no.) | Uttar Pradesh | 31.12.2013 | 0.53 | 105 | |||
| 31.08.2014 | |||||||||
| 46 | Jakson engineers Noida | Power plants (3no.) | Karnataka, Tamilnadu | 31.12.2013 | 0.89 | 280 | 80kWp installed so far | ||
| 31.08.2014 | |||||||||
| 47 | JJ PV Solar Rajkot | Power | Gujarat | 31.12.2013 | 1.1 | 246 | 55kWp installed so far | ||
| Plants/pumps | 31.08.2014 | ||||||||
| 48 | Lubi | Power Plant | Gujarat | 31.12.2013 | 0.15 | 50 | |||
| Electronics Ahmadabad | 31.08.2014 | ||||||||
| 49 | Novus Green Hyderabad | Power Plants (7no.) | Andhra Pradesh | 31.12.2013 | 2.61 | 510 | 205kWp installed | ||
| 31.08.2014 | |||||||||
| 50 | PAE | Power Plants (10no.) | Karnataka ,Maharashtra | 31.12.2013 | 1.48 | 398 | 158kWp installed | ||
| Renewables Mumbai | 31.08.2014 | ||||||||
| 51 | Power One | Power plants (45no.) | Karnataka ,Kerala | 31.12.2013 | 0.45 | 89 | Completed | ||
| Micro | 31.08.2014 | ||||||||
| Bangalore | |||||||||
| 52 | PPS Enviro Hyderabad | Power Plants (4no.) | Andhra Pradesh, Tamilnadu | 31.12.2013 | 0.52 | - | 145 | ||
| 31.08.2014 | |||||||||
| 53 | Pulse Power Kolkata | Power Plants (6no.) | West Bengal, Rajasthan | 31.12.2013 | 0.53 | - | 179 | ||
| 31.08.2014 | |||||||||
| 54 | Radiant Solar | Power Plants (5no.) | Kerala | 31.12.2013 | 0.49 | 151 | Completed | ||
| Hyderabad | Andhra Pradesh | 31.08.2014 | |||||||
| 55 | Rfrex Mumbai | Power Plant | Andhra Pradesh | 31.12.2013 | 0.29 | - | 98 | Completed | |
| 31.08.2014 | |||||||||
| 56 | Statcom Noida | Power Plants (20no.) | Uttar Pradesh, Tamilnadu | 31.12.2013 | 2.08 | - | 438 | ||
| 31.08.2014 | |||||||||
| 57 | Servomax Hyderabad | Power Plants (2no.) | Andhra Pradesh | 31.12.2013 | 0.43 | - | 87 | ||
| 31.08.2014 | |||||||||
| 58 | Sun Edison Chennai | Power Plants (20no.) | Tamilnadu, Maharashtra ,Madhya Pradesh | 31.12.2013 | 4.86 | 1651 | |||
| 31.08.2014 | |||||||||
| 59 | Sun Energy | Power Plants (4no.) | Gujarat | 31.12.2013 | 0.66 | 218 | Completed | ||
| Systems | 31.08.2014 | ||||||||
| Anand | |||||||||
| 60 | Sun Source New Delhi | Power Plants (13no.) | Delhi, Tamilnadu, Haryana | 31.12.2013 | 3.56 | - | 1208 | ||
| 31.08.2014 | |||||||||
| 61 | Swelect | Power Plants (22no.) | Tamilnadu | 31.12.2013 | 1.13 | 354 | |||
| Energy | 31.08.2014 | ||||||||
| Chennai | |||||||||
| 62 | Tata Power Bangalore | Power Plants | Various states | 31.12.2013 | 5.77 | - | 1998 | ||
| 31.08.2014 | |||||||||
| 63 | Tata power Bangalore | Power Plants | Various states | 31.12.2013 | 4.48 | - | 1714 | ||
| 31.08.2014 | |||||||||
| 63 | Thakaral | Power Plants | Various states | 31.12.2013 | 1.16 | 221 | Completed | ||
| Service | 31.08.2014 | ||||||||
| Bangalore | |||||||||
| 64 | Thermax Pune | Power plants (10no.) | Gujarat Maharashtra | 31.12.2013 | 1,07 | - | 398 | Completed | |
| 31.08.2014 | |||||||||
| 65 | Top Sun Gandhinagar | Power Plant (3no.) | Gujarat | 31.12.2013 | 0.26 | - | 90 | ||
| 31.08.2014 | |||||||||
| 66 | Veddis Solar Hyderabad | Power Plants (55no.) | Bihar | 31.12.2013 | 1.04 | - | 189 | ||
| 31.08.2014 | |||||||||
| 67 | Vikram | Power plant | Assam | 31.12.2013 | 0.51 | 100 | Completed | ||
| Solar | 31.08.2014 | ||||||||
| Kolkata | |||||||||
| 68 | Waree energy Mumbai | Power Plants (4no.) | Rajastahn Gujarat | 31.12.2013 | 0.61 | 240 | |||
| 31.08.2014 | |||||||||
| 69 | Zodiac Energy Ahmadabad | Power Plants (5no.) | Gujarat | 31.12.2013 | 0.71 | 237 | |||
| 31.08.2014 | |||||||||
| 70 | Zpdiac Energy Ahmadabad | Power Plants (4no.) | Gujarat | 31.12.2013 | 0.47 | 158 | |||
| 31.08.2014 | |||||||||
| 363.08 | 15.72 |