Coal resource available in existing CIL blocks is about 88.42 billion tonnes
Production target of Coal India Limited for 2014-15 is 507 MT
July 15, 2014. By Moulin
The production target of Coal India Limited for 2014-15 is 507 MT. Details of monthly targets of coal production of CIL vis.-a-vis actual production during the last four months percentage achievement along with quantum of coal supplied to private sector power generation companies under linkage are given below:
| (in million tonnes) | ||||
|
Month |
Target |
Production |
% Ach. |
Supply to private sector Power generation companies. |
|
March, 2014 |
52.71 |
53.40 |
101.3 |
4.07 |
|
April, 2014 |
37.61 |
37.51 |
99.7 |
3.38 |
|
May, 2014 |
38.56 |
36.28 |
94.0 |
3.66 |
|
June, 2014* |
36.84 |
34.55 |
93.8 |
NA |
| * Provisional | ||||
- Law and order problem in MCL and CCL
- Delay in getting Forest clearance and Environmental Clearance.
- Frequent Breakdown of Draglines at NCL and WCL causing less exposure of coal (iv) Less transportation of coal by ESM company in SECL
- Restriction of working hours from 10.30 AM to 3.30 PM imposed by State Government due to heat wave in MCL.