3.6% electricity was generated by nuclear power in India in the year 2012
India has total 20 nuclear power plants with installed capacity of 4780 MW
December 13, 2013. By Moulin
The share of nuclear power in total electricity generation in the year 2012 in India was about 3.6%. The share of nuclear power generation in some of the other nuclear power generating countries are as under:-
|
Country |
Nuclear Share(%)
|
|
France |
74.8 |
|
USA |
19.0 |
|
UK |
18.1 |
|
Russian Federation |
17.8 |
|
Korea |
30.4 |
|
China |
2.0 |
There are 20 nuclear power plants with installed capacity of 4780 MW. Of these 19 reactors with an installed capacity of 4680 are currently operating. One reactor, Rajasthan Atomic Power Station (RAPS) unit-1 (100MW) is under extended shutdown for techno-economic assessment for continued operation. The details of nuclear power plants operating in the country are as under:
Unit |
Reactor Type |
Capacity (MW) |
Commencement of Commercial operation |
|
|
Tarapur, Maharashra |
||||
|
1 |
TAPS-1 |
BWR |
160 |
28 Oct. 1969 |
|
2 |
TAPS-2 |
BWR |
160 |
28 Oct. 1969 |
|
3 |
TAPS-3 |
PHWR |
540 |
18 Aug. 2006 |
|
4 |
TAPS-4 |
PHWR |
540 |
12 Sept. 2005 |
|
Kakrapar, Gujarat |
||||
|
1 |
KAPS-1 |
PHWR |
220 |
06 May 1993 |
|
2 |
KAPS-2 |
PHWR |
220 |
01 Sept. 1995 |
|
Rawatbhata, Rajasthan * |
||||
|
1 |
RAPS-2 |
PHWR |
200 |
01 Apr. 1981 |
|
2 |
RAPS-3 |
PHWR |
220 |
01 June 2000 |
|
3 |
RAPS-4 |
PHWR |
220 |
23 Dec. 2000 |
|
4 |
RAPS-5 |
PHWR |
220 |
04-Feb-2010 |
|
5 |
RAPS-6 |
PHWR |
220 |
31-Mar-2010 |
|
Narora, Uttar Pradesh |
||||
|
1 |
NAPS-1 |
PHWR |
220 |
01 Jan. 1991 |
|
2 |
NAPS-2 |
PHWR |
220 |
01 July 1992 |
|
Kaiga, Karnataka |
||||
|
1 |
KAIGA-1 |
PHWR |
220 |
16 Nov. 2000 |
|
2 |
KAIGA-2 |
PHWR |
220 |
16 Mar. 2000 |
|
3 |
KAIGA-3 |
PHWR |
220 |
06 May 2007 |
|
4 |
KAIGA-4 |
PHWR |
220 |
20-Jan-2011 |
|
Kalpakkam, Tamil Nadu |
||||
|
1 |
MAPS-1 |
PHWR |
220 |
27 Jan. 1984 |
|
2 |
MAPS-2 |
PHWR |
220 |
21 Mar 1986 |
*RAPS-1 (100 MW) is under extended shutdown since October 2004
There are seven nuclear power reactors at various stages of construction/commissioning of which one reactor, Kudankulam Nuclear Power PlantUnit-1 (1000 MW) has already been connected to the grid in October 2013, generating firm power. The details of other reactors under construction/commissioning are as follows:-
|
Project |
Location |
Capacity (MW) |
Status |
|
KKNPP Unit-2 |
Kudankulam, Tamil Nadu |
1x1000 |
Under commissioning |
|
KAPPUnits 3&4 |
Kakrapar, Gujarat |
2x700 |
Under construction |
|
RAPP Units7&8 |
Rawatbhata, Rajasthan |
2x700 |
Under construction |
|
PFBR |
Kalpakkam, Tamil Nadu |
1x500 |
Under construction |
Currently, there is no proposal to set up a nuclear power plant in Jharkhand. In order to locate a nuclear power plant at a given site, the site has to fulfill several criteria stipulated by the Atomic Energy Regulatory Board. A suitable site, meeting these criteria, has not been identified in the State so far.
Minister of State for Personnel, Public Grievances & Pensions and Prim Minister’s Office Shri V.Narayansamy gave this information in reply to a written question in the Rajya Sabha .
please contact: contact@energetica-india.net.