POWERGRID Acquires SPV for 6 GW Barmer RE Evacuation Project
POWERGRID has acquired the Barmer HVDC Power Transmission SPV for a 6 GW renewable energy evacuation project from Barmer, Rajasthan, involving a ±800 kV, 6,000 MW HVDC system and an approximately 1,000-km transmission line to South Kalamb.
RE Evacuation From Barmer Complex | September 24, 2026 | By Mrinmoy Dey | 1095
POWERGRID Wins ISTS Project to Evacuate 6 GW of Renewable Energy from Rajasthan
POWERGRID has won a tariff-based competitive bidding process to develop an ISTS project for evacuating 6 GW of renewable energy from Rajasthan’s Barmer Complex, with annual transmission charges of INR 3,244.33 crore.