ACME Solar Commissions Additional 19.8 MW of its Maiden Wind Project in Gujarat

Following the initial commissioning of 26.4 MW in May 2025, the company in current phase has commissioned an additional 19.8 MW taking the total commissioned capacity of the wind project to 46.2 MW out of the planned 50 MW.

Maiden Wind Project In Gujarat | June 13, 2025 | By News Bureau 749