CERC Introduces Structured MEC Mechanism for Delayed GNA Milestones

Central Electricity Regulatory Commission has finalised a GNA milestone extension mechanism, allowing eligible projects additional time against MECs of INR 1,000/MW/day for land (up to 3 months) and financial closure (up to 6 months), and INR 3,000/MW/day for COD (up to 12 months), rising to INR 6,000/MW/day in months 10–12.

GNA Regulations | August 17, 2026 | By Mrinmoy Dey 338

CERC Issues Order Clarifying GNA Rules, Grants Relief to Renewable Developers

CERC issued an order to remove difficulties in implementing GNA regulations, streamlining ISTS connectivity and easing industry challenges.

GNA Regulations | December 10, 2025 | By EI News Network 2360