HomeSmart Grid / T&D ›Sterlite Power commissions two 400KV lines in State of Telangana.

Sterlite Power commissions two 400KV lines in State of Telangana.

Sterlite Power commissions 400KV D/C Nizamabad-Shankarapally and 400KV Maheshwarm-Mehboobnagar Lines.

February 13, 2018. By Moulin

Sterlite Power has successfully commissioned the 400KV D/C Nizamabad-Shankarapally and 400KV Maheshwarm-Mehboobnagar linesin the newly formed State of Telangana, well ahead of the scheduled date. These lines are integral part of the State government towards ensuring adequacy of the system to provide reliable and quality power to the consumers in the state.

Dedicating the project to the State, the CEO of Global Infrastructure BU, Sterlite Power, Ved Tiwari said, “The State has embarked on a timely journey to upgrade its transmission system towards meeting the projected peak load of over 21,000 MW upto FY 2018-19 and RE power of about 6,016 MW. These lines augment the power off take capacity by almost 1000 MW and should help in addressing the increase of household consumption to 3.56 units/ day in FY 2018-19.”

He added, “Specific to the project, as the existing bays were more than 15 years old and designs unavailable, our team prepared the same by physically tracing the existing scheme for integration. This resonates with our purpose – empowering humanity by addressing the toughest challenges of energy delivery.” 

Please share! Email Buffer Digg Facebook Google LinkedIn Pinterest Reddit Twitter
If you want to cooperate with us and would like to reuse some of our content,
please contact: contact@energetica-india.net.
 
 