Our Company |   Join Our Club |      

news categories



news per location



May / June 2016



Read our bloggers



Power Plants



  • Directorio de Eficiencia energética

Over $500 million Law Suit against Suzlon

Jump to the comments
Trinity Structural Towers, Inc. (TSTI), a subsidiary of Trinity Industries, Inc. has announced that it has filed a breach of contract law suit against Suzlon Wind Energy Corporation for failure to comply with its purchasing obligations for structural wind towers from TSTI pursuant to the 2008 Supply Agreement between the two companies. The law suit was filed in the District Court of Dallas County.

In accordance with the Agreement, Suzlon agreed to purchase approximately $377.3 million worth of TSTI manufactured 80-meter wind towers on a scheduled basis through 2011. Following the execution of the Agreement, TSTI and Suzlon mutually agreed to amend the Agreement on two separate occasions, ultimately resulting in an additional $123.8 million worth of wind towers to be purchased and extending the delivery timeframe of wind towers through 2013.

To date, TSTI has produced and delivered approximately $88.6 million worth of wind towers, excluding price adjustments related to materials costs, applicable to the aggregate wind tower purchase obligation agreed upon under the Agreement, as amended. TSTI claims that Suzlon has breached its contractual purchase obligations for 2010 and 2011 by failing to take delivery of its obligated number of wind towers during this period. In addition, Suzlon has not yet secured its 2012 and 2013 production space for its obligated purchase of wind towers in each of these years.

TSTI has incurred, and continues to incur, damages as a result of Suzlon’s alleged breach of its purchase obligations. TSTI has been, and remains willing and able, to perform its obligations under the agreement, as amended.

Suzlon’s remaining purchase commitment under the Agreement, as amended, represents approximately $412.5 million of TSTI’s total wind tower backlog of approximately $929.5 million as reported on September 30, 2011. The wind towers pertaining to the Agreement remain in TSTI’s backlog, pending an outcome in the litigation.
Wind Power | News published on 11 / 01 / 2012 by Andrew Callaway

Comments in this news Add yours

There are no comments. Add your comment

  Other Interesting News

Suzlon foresees to build 2000MW Wind Energy projects over next five years in MP Deutsche Bahn earns top place in the prestigious climate protection ratings REpower launches 3-MW turbine for low-wind locations in Canada GE to supply 9F 3-series gas turbines to Bangladesh JSW Energy Ltd. board approves results for the quarter ended September 30, 2013